Yalumba Reserve Building and Carpark Upgrade Status Report 3

Address
Anticipated completion date

Current Status: The project is now four weeks behind schedule due to weather delays and the delay in the structural steel delivery. We have brought forward the civil works.

Achievements this period: Services from new build to the street.

Forecast Achievements for next period: Structural steel.