Lakeview Drive, Parafield Gardens
- Type
- Roads and parking
- Status
- Works underway
- Anticipated completion date
- 30 September 2025
Scope of work
This project focuses on improving vehicular efficiency and safety at the intersection of Lakeview Drive and Kings Road, Parafield Gardens. The roadway will be widened to create dedicated left and right turn lanes from Lakeview Drive onto Kings Road, with lighting along this portion of roadway improved as part of these works. In order to facilitate the widening of the roadway, some small trees will be removed within the verge along Lakeview Drive.
Timing
VMS boards advising of the upcoming works are being installed today, Monday 14 July 2025.
Preliminary site investigation and set out, including tree removal will commence from Wednesday 16 July, with site mobilisation expected to commence from 21 July, weather dependent.
These works are expected to take 4-6 weeks.
Traffic management will be in place, with detours via Salisbury Highway.